In a project schedule, which types of dependencies are most common?

Respuesta :

eylumamaho7
eylumamaho7 eylumamaho7
  • 07-05-2021
Finish to start dependency- This is the most common type of dependency in project management as well as real life.
Answer Link
iwannak iwannak
  • 13-05-2021

Answer:

Finish to Start, finish to finish.

Explanation:

Answer Link

Otras preguntas

Please show your work !!!!!!!!!!!! Will mark Brianliest !!!!!!!!!!!!!!!!!
if the original quantity is 14 in the new quantity is 24 estimate the percent change​
If the sum of x and y is 90 and y is 6 more than four times x, which of the following systems of equations could be used to solve for x and y? A.x+y=90 x−4y=6 B
Themes are specific and can only apply to a certain group of people. true or false
Which one is true about the diagram?
h divide 4 = 9 I need help with this​
Anaerobic and aerobic respiration both begin with... 1. The conversion of light into glucose 2. The breakdown of glucose 3. The formation of water to release s
I need help with history.
What is the quotient of 63 and 0
Which word best completes the statement? Carolina y Pedro son mis tíos. Sus hijos son mis _____. A. hermanas B. primas C. tíos D. primos