The work component at the lowest level of the WBS for which cost and duration can be estimated and managed is called the ______:

Respuesta :

dvynnjoku dvynnjoku
  • 07-01-2020

Answer:

The answer is Work Package.

Explanation:

Work Package is the work component at the lowest level of the work breakdown structure(WBS), for which cost and duration can be estimated and managed; beyond this level, further decomposition will not be done.

Work packages are the primary input to identify activities' process. They are planned by way of identifying activities under them.

Answer Link

Otras preguntas

Which explains why carbon is a component of so many elements? A. It appears in more than one form B. It is the most abundant element C. It can react with both m
93 is what percent of 60
How many times was King arrested during his life? a. 39 b. 19 c. 29 d. 9
To paraphrase a poem means to A. analyze the meter. B. summarize its theme. C. rewrite it in one's own words. D. determine the rhyme scheme.
What is the solution pf the eqation??? x/3= -6
How many times was King arrested during his life? a. 39 b. 19 c. 29 d. 9
King led an important protest against what on April 3, 1968? a. slavery b. poverty c. discrimination d. starvation in India
Tommy has been asked to write a 1-page essay about recycling. He decides to write about biodiesel, which is a fuel that is made from recycled oil. Which of th
FILL IN THE BLANK PLZ HELP françois demande s'il peut emprunter son chapeau il Pense vraiment qu'il est tellement ________. WORDS: Même Mains Voit Fâchée Ami
The acronym M.A.D. stood for