kiritokun3397 kiritokun3397
  • 06-06-2023
  • Business
contestada

In an earned value reporting system, the status of the project is reported as PV=100,AC=110 and EV=95. Your evaluation shows that the project is now: a. Under spent and ahead of schedule b. Overspent and behind schedule c. Overspent and ahead of schedule d. Under spent and behind schedule

Respuesta :

Otras preguntas

A number has 6 hundreds, 7 tens, and 34 ones. What is the number?
How did the Great Depression eventually change Germany politically?
Which was NOT a motivation for European exploration in the fifteenth and sixteenth centuries? A:the desire for wealth B:ottoman control of the Silk Road C:the r
What are the chief landforms in the Midwest in Great Plains region
A number has 6 hundreds, 7 tens, and 34 ones. What is the number?
why the climate is so hot near the equator?
Can someone help me with a thesis for revenge ?
a chess player played 20 games total. if he won 2 of the games, what is the ratio of games he lost to games he won?
a chess player played 20 games total. if he won 2 of the games, what is the ratio of games he lost to games he won?
2/3 0.5 3/5 0.65 smallest to biggest I need the answer now ?