Two companies working together can clear a parcel of land in 18 hours. Working alone, it would take
Company A 10 hours longer to clear the land than it would Company B. How long would it take
Company B to clear the parcel of land alone?

Respuesta :

Otras preguntas

What are 'blighting influences'
a computer downloaded 20 kilobytes of data in 4 seconds. if it downloads data at a constant speed, it can download ______ kilobytes of data in 15 seconds.
i'm 1679 new hampshire was established as a ______ colony
How did the renaissance providing the excitement and innovation that led to global explanation
What do sessile animals eat
what powers the water cycle
henry viii had a major impact on the reformation
Adult tickets to the fall play cost $6 and student tickets cost $3. The drama class sold 25 more student tickets than adult tickets to the fall play. If the cla
You are alone and have identified a child who is not responsive. You have performed chest compressions for 2 minutes. What is the next step in CPR? A. Try to
what plant did the haudenosaunee called the three sisters